Reference No: ECO0066(B)Pages: 4Published on: 1, January, 1968
Abstract: Deals with the issue of compensation as a result of nationalization of the air transport industry. The various schemes for compensation considered by the Government of India are mentioned in the case. The case is used for encouraging the student to appraise the fairness or otherwise of the schene adoped ... More
Reference No: PROD0063Pages: 11Published on: 1, January, 1968
Abstract: This is an integrated case about a small business enterprise that manufactures plastic consumer items. It provides sufficient scope for improving the company's production operations as well as for developing the strategy that should be followed by this company. ... More
Reference No: PROD0005Pages: 11Published on: 1, January, 1968
Abstract: The production director wants to review the company's incentive scheme. The case gives the history and nature of the scheme in detail. The student is required to point out the merits and defects of the scheme and suggest suitable improvements. ... More
Reference No: PROD0038Pages: 3Published on: 1, January, 1967
Abstract: An actual situation is described to illustrate the application of line of balance technology. It could also be used as an exercise case. The discussion could be centered on the usefulness of line of balance technology in a manufacturing situation. ... More
Reference No: QM0029Pages: 7 Published on: 1, January, 1967
Abstract: Students are required to compute the relevant costs of existing methods of production, and compare them with the costs of an automated operation. ... More
Reference No: PROD0045(A)Pages: 13 Published on: 1, January, 1967
Abstract: The case describes a large maintenance depot of a transport organization and the maintenance schedules followed by the depot with respect to their fleet of buses. It also describes the detailed operations. Because of the restricted time available for the maintenance, the depot manager has to devise a method of ... More
Reference No: PROD0053Pages: 12Published on: 1, January, 1967
Abstract: Describes a problem faced by the management wherein a decision has to be made whether to buy a Turret Lathe or an Automat to replace the worn-out Turret Lathe. Facts and figures on equipment cost, and operating and maintenance costs for the two types of equipment are given. Students are ... More
Reference No: MAR0062(D)Pages: 9Published on: 1, January, 1967
Abstract: This is the fourth case in the series, describing the inferences drawn and the recommendations put forward by the research agency to the client. Students are expected to play the role of the decision maker and use the information to arrive at specific decisions. The question of reliability and relevance ... More
Reference No: PROD0026(B)Pages: 6Published on: 1, January, 1967
Abstract: Outlines the detailed discussions that took place between the case writer and the PERT administrator of the company. It highlights the problems the company had to face in working with PERT and also the way it solved them. The administrator describes his reactions, attitudes and dealings with the company's supervisory ... More
Reference No: PROD0050Pages: 18Published on: 1, January, 1967
Abstract: Describes the collaborative efforts of a national laboratory and a large?sized company. The company makes use of a new process developed by the laboratory for a finished product (baby foods) and succeeds in setting up a plant. The case also discusses the types of difficulties the company has had ... More
Reference No: PROD0034TECPages: 20Published on: 1, January, 1967
Abstract: The note explains four advanced applications of PERT networks: 1) scheduling with limited resources, 2) time? cost trade?offs, 3) network cost control systems, and 4) statistical approach in PERT scheduling. The existing rules and procedures for their use have been illustrated by examples. ... More