Abstract
Fertilizer. She is currently planning a critical shutdown in the nitric acid plant. The plant would incur a penalty anywhere between ₹10 to ₹15 lakh per hour for delays. Akshara should use the critical path method (CPM) in scheduling tasks and identify the critical path to decrease the overall time required for these tasks and prevent penalty payments. Each activity involves trade-offs in cost and time involved. Her success in this project is crucial for career advancement.
Additional Information
| Product Type | Exercise |
|---|---|
| Reference No. | O&DS0007(C)EX |
| Title | SYS Fertilizers (C): Project Management |
| Pages | 3 |
| Published on | Jan 6, 2025 |
| Authors | Shinde, Shubham A; Parameshwari, Yoga M; Narayanaswami, Sundaravalli ; |
| Area | Operations & Decision Sciences (O&DS) |
| Discipline | Management Education , Operations Management, Quantitative Methods |
| Sector | Agriculture and Animal Husbandry, Manufacturing |
| Learning Objective | This case provides an opportunity to apply the Critical Path Method and schedule the tasks effectively by minimizing the overall project duration. The case creates scenarios where the completion timeline should be considered to avoid the penalty due to delay. Making decisions on cost-time trade-offs to optimize the shutdown process, i.e. balancing between minimizing time and costs. Creating a schedule for shutdown operation by considering various interdependent activities to meet the timeline. |
| Keywords | CPM; Critical Path; Crashing; Project Management; Scheduling; Shift Management |
| Country | India |
| State | Maharashtra |
| City | Mumbai |
| Access | For All |